Window installation is underway at Pier 27 phase 1 and the crew will be doing testing this week. The first SkyBridge is structurally complete and the second is about 40 per cent done.
Window installation will begin in the next few weeks on phase 2 with drywalling and stud work set to begin in the next month or so. Below grade, plumbers and electricians are working away in the garage where drywall will be installed in the next couple of weeks. Here's what was happening on site on a rather overcast Friday last week.