The Southwest Quadrant Renewal Plan for Brampton City Hall is well and truly underway, with our Dominus crew having commenced work on site back in February of this year.
We visited Brampton last week to check in on what's been happening and can report that progress on site is continuing at pace and we expect to remain on schedule.
The caisson wall, king piles and soldier piles are all completed and the process now is to dig as long and as deep as we can to start strutting in the next couple of weeks.
The aim at the moment is to mobilize the formwork this summer, with Verdi Alliance recently confirmed as the formworkers for the project.
Once underway, there will be two tower cranes on site, temporary power for the cranes, hoist and workers tools and a gas line will be installed soon for temporary heat for the winter months.
Check out our latest images from on site below.
We'll be back with another look at progress on site soon. In the meantime, if you have any questions let us know in the comments box below, or join the conversation on Facebook and Twitter.