Designed by architectsAlliance and interior designer Munge Leung, Pier 27 will luxuriously accommodate 303 units and 15 storeys on the waterfront. Here is the latest on construction at Pier 27.
In Phase 1, the 12th floor has been poured on building one. The 8th floor on building two will be poured by the end of the week.
In Phase 2, the fourth floor of building one is complete, and at building two the 2nd floor is complete.
For now, we have to finish Phase 1 and 2 before we move on to Phase 3 which will consist of two short buildings and one tall building in total.
Pier 27's iconic bridge (pictured in the top rendering) will be under construction in June and with expected structural completion by the end of July.
See our last Pier 27 construction update: January 2012. Oh, and here's our favourite shot: