Daniel Libeskind's building is elevating, accelerating and propelling forward steadily. At L Tower, we're pouring level 35 this week. Our crew is on a four-day cycle, so a floor is being carried out every four days. Of course, it helps that the weather has been pleasant.
L Tower's low-rise elevator door frames will be completed this week and will virtually wrap up by the end of next week. The cabs are currently being set up on the mid-rise elevators, and we're putting finishing touches to them this week. Sooner than later, the high-rise elevator construction work will start soon.