Our last L Tower construction update was in mid-November, and since then, we've shared tons about Daniel Libeskind but not enough about the progress of his latest Toronto building. So what's new at the L?
The highly anticipated building is currently built up to the 23rd floor and continuing at a pace of roughly one floor built per week.
Windows have been delivered with some initial installations on the 4th floor with more on the way.
We've received a delivery of windows up to the 9th floor so work will progress on installation in the coming weeks.
Plumbing, electrical, and water work will be starting in the next few weeks so our already busy site is about to get a whole lot busier.
The Sony Centre Back of House work has also been coming along nicely.
L Tower is one of our most exciting projects yet that screams "starchitect". We are beyond excited to see the final project and how it will effect the Sony Centre's revitalization.
For all of our latest construction photos for L Tower, see our Facebook album. Anything you'd like to see in the next construction update? Let us know!